Mordhana Dam releases water for irrigation after completing canal desilting work
Water Resources Department completes desilting of Mordhana Dam canals ahead of nine-day irrigation water release benefiting 2,500 acres across Vellore.
The Water Resources Department has completed desilting of Mordhana Dam's main canals ahead of a nine-day water release that began for irrigation until September 1, countering claims by the local MP that the channels remained clogged.
A 20-member maintenance team cleared the left and right canals before Collector P.S. Leena Alex and WRD officials opened the sluices to release an average 225 cusecs daily, totalling 174.96 mcft over the period, to recharge groundwater at least 10 kilometres downstream. "Based on requests from farmers, water has been released to fill tanks downstream," S. Kalipriyan, Assistant Engineer (Gudiyatham), told The Hindu.
MP flags tail-end irrigation risk
Vellore MP D.M. Kathir Anand had alleged in a press release that incomplete desilting of canals and feeder channels would impair water flow, particularly in tail-end areas. The WRD rejected the charge, pointing to periodic maintenance carried out before the scheduled release.
Left canal restored under state scheme
The left canal, which runs 31.84 km across 19 villages covering 1,710.92 hectares of farmland, underwent restoration in July 2025 under the Rehabilitation and Restoration of Lakes scheme 2024-25. Silt deposited over years of cultivation was excavated to a depth of three metres, and thick vegetation on bunds and slopes was cleared to ensure steady flow. The canal, three metres wide, serves the ayacut areas of seven tanks.
Water to benefit 2,500 acres, nine tanks
The reservoir, built across the Koundinya River, a Palar tributary, currently holds 235.03 mcft against a total capacity of 261.3 mcft. The release will benefit nine tanks in Gudiyatham and Katpadi taluks, enabling cultivation on around 2,500 acres and recharging groundwater in their vicinity. While the Koundinya directly irrigates 140 acres, another 220 acres are served by the canals.
"Water from the dam will help cultivate paddy, groundnuts, and banana along the river as most of the water bodies have become dry. Most farmers in the region depend on borewells for irrigation," said T. Pasupathi, a farmer.
Source: The Hindu
Frequently asked questions
What work did the Water Resources Department complete at Mordhana Dam?
The Water Resources Department completed desilting of Mordhana Dam's main canals, clearing the left and right canals with a 20-member maintenance team before releasing water for irrigation.
How much water was released and for how long?
Water was released for nine days until September 1 at an average of 225 cusecs daily, totalling 174.96 million cubic feet over the period, to recharge groundwater and fill tanks downstream.
What restoration work was done on the left canal?
The left canal, which runs 31.84 km across 19 villages, underwent restoration under the Rehabilitation and Restoration of Lakes scheme 2024-25 in July 2025, with silt excavated to a depth of three metres and vegetation cleared from bunds and slopes.
How many acres and which crops will benefit from this water release?
The water release will benefit around 2,500 acres across nine tanks in Gudiyatham and Katpadi taluks, enabling cultivation of paddy, groundnuts, and banana, and recharging groundwater in the region.
Most read
- 1
Tesla audits Chinese suppliers to scale up Optimus robot production
- 2
Former minister Lakhan Singh Rajput to inaugurate temple bhandara at Shri Chakreshwar Mahadev
- 3
Firozabad BSA finds four government schools locked during inspection
- 4