Road diversion on Prayagraj bridge doubles commuter costs, delays journeys
A route diversion imposed on the Fafaramau Ganga Bridge in Prayagraj to ease congestion has become a growing source of trouble for both the transport corporation and passengers traveling between
A route diversion imposed on the Fafaramau Ganga Bridge in Prayagraj to ease congestion has become a growing source of trouble for both the transport corporation and passengers traveling between Pratapgarh and Prayagraj. The diversion, which was put in place in view of the traffic jam problem on the Fafaramau Ganga Bridge, applies to large and heavy vehicles and has forced Roadways buses operating between the two cities to take a longer detour via Soranv, Sahson and Jhunsi.
The extended route has had a direct impact on passengers' pockets. Earlier, the fare for a Roadways bus from Pratapgarh to Prayagraj was 93 rupees, but after the diversion the fare has increased to 120 rupees due to the additional distance covered. This means passengers now have to spend an extra 27 rupees for a one-way journey alone.
Apart from the fare hike, travel time has also increased significantly. Passengers say that because of the diversion, reaching Prayagraj now takes considerably longer than it used to. This has particularly affected daily commuters who travel to and from Prayagraj regularly, and they are facing the maximum inconvenience.
Travelers have expressed concern that if the diversion continues for an extended period, the additional burden of both higher fares and increased travel time will weigh heavily on people. For the transport corporation, operating buses on the longer route is also proving to be an increasing challenge. The diversion, originally meant to address congestion on the bridge, has thus ended up creating fresh difficulties for the roadways system and the traveling public alike, with no immediate relief in sight for regular passengers on this busy corridor.
Frequently asked questions
Why has the fare from Pratapgarh to Prayagraj increased?
The fare has increased from 93 rupees to 120 rupees due to a route diversion imposed on the Fafaramau Ganga Bridge. Large and heavy vehicles, including Roadways buses, must now take a longer detour via Soranv, Sahson, and Jhunsi, covering additional distance that resulted in the 27 rupee fare increase.
What is the reason for the route diversion on Fafaramau Ganga Bridge?
The diversion was put in place to ease congestion and address traffic jam problems on the Fafaramau Ganga Bridge. It applies to large and heavy vehicles traveling between Pratapgarh and Prayagraj.
How has the diversion affected travel time between Pratapgarh and Prayagraj?
Travel time has increased significantly due to the longer detour route. Passengers report that reaching Prayagraj now takes considerably longer than before, particularly affecting daily commuters who travel regularly between the two cities.
Who is most impacted by the route diversion?
Daily commuters traveling regularly between Pratapgarh and Prayagraj are facing maximum inconvenience due to both higher fares and increased travel time. The transport corporation is also experiencing challenges operating buses on the longer route.
Most read
- 1
Tesla audits Chinese suppliers to scale up Optimus robot production
- 2
Former minister Lakhan Singh Rajput to inaugurate temple bhandara at Shri Chakreshwar Mahadev
- 3
Firozabad BSA finds four government schools locked during inspection
- 4
Tamil Nadu dengue cases fall for third consecutive year to 17,049
- 5
Social workers stage silent protest at Fufund railway station for train halts
Comments
No comments yet. Be the first to comment.