JSW Steel is building a 13.2 MTPA greenfield integrated steel plant at Paradip, Odisha, through its arm JSW Utkal Steel.
The project spans about 2,950 acres along the Odisha coast with an estimated investment near Rs 65,000 crore, part of a larger cumulative commitment of around Rs 1.25 lakh crore. Production is expected to begin around 2028-29.
Key Points - Developer: JSW Steel, through JSW Utkal Steel Limited. - Location: Paradip, on Odisha's coast, with port connectivity and raw-material access. - Capacity: 13.2 million tonnes per annum (MTPA), to be built in phases. - Land: Approximately 2,950 acres.
- Investment: About Rs 65,000 crore for the plant; cumulative complex commitment near Rs 1.25 lakh crore. - Timeline: Steel production expected to start around 2028-2029.
Project at a Glance | Parameter | Detail | | --- | --- | | Company | JSW Steel (JSW Utkal Steel Ltd) | | Location | Paradip, Odisha | | Capacity | 13.2 MTPA (phased) | | Land area | ~2,950 acres | | Estimated investment | ~Rs 65,000 crore (cumulative ~Rs 1.25 lakh crore) | |
Expected production start | ~2028-2029 | | Type | Greenfield integrated steel plant | Frequently Asked Questions Where is JSW's new steel plant in Odisha located? At Paradip on the Odisha coast, developed by JSW Utkal Steel Limited.
What is the capacity of the JSW Odisha steel plant? The plant is planned for 13.2 million tonnes per annum (MTPA), to be built in phases. How much is JSW investing in the Odisha plant?